Plan the spring reroof mail season backwards from your first install date: pull the list in January, finish creative and print in February, drop the first touch in late February or March, and run the second and third touches through May, with each drop sized to what your crews can actually install. Scout Data (ours) delivers lists of homes by roof age and roof condition, with homes already re-roofed taken out, ready for the first drop.
Disclosure: Scout Data is our product; treat that entry as a maker’s pitch and the rest as our honest read.
Why spring mail has to be planned in winter
In markets without regular storms, reroof demand follows the calendar. Owners notice their roof after winter (ice dams, a leak, granules in the gutters) and want it done before summer. The mail that books those jobs has to land in late winter and early spring, which means the work behind it happens in December and January. Teams that start planning in March are mailing into the season instead of ahead of it. For why owners decide when they do, see reroof timing and how to target it.
A backwards calendar from first installs
The calendar below assumes installs start in early April, which is common in the Northeast and upper Midwest. Shift every step earlier for a warmer market and later for a colder one.
December: set the goal and the budget
Decide how many jobs you want from spring mail, how many your crews can install per week, and what you can spend. Agree on the ZIP codes and the list filters (for example, owner-occupied asphalt shingle homes with roofs around 18 years and older).
January: pull and clean the list
Pull the list, send it to your mail house, and apply your suppressions: past customers, homes already re-roofed, open leads, do-not-mail requests. Get the final mailable count after CASS and NCOA so the print quote is real. See sending a roofing list to your mail house for the file and suppression setup.
February: creative and print
Write and approve all three pieces at once (letter, postcard, final offer) so the sequence reads as one campaign. Order tracking numbers or codes per drop. Print the first touch; the mail house can hold the others or print them closer to each drop.
Late February to March: first touch
Drop the letter. USPS Marketing Mail delivery windows vary by distance and entry point and can stretch past a week, so set the drop date with a cushion and check current service standards on usps.com. A first touch that lands in early March gives owners time to book inspections before installs open.
April to May: second and third touches
Send the postcard a few weeks after the letter and the final offer a few weeks after that, removing anyone who has already responded. The last touch should land while you still have install weeks open before summer.
Splitting the budget across touches
A simple way to start is to give the first touch the largest share, because it goes to every home, and let the second and third touches go only to non-responders. Say, for illustration, a 300,000-home list at about 45 cents a piece all-in: the first touch is roughly $135,000, and each later touch costs a little less because responders and returned mail come out. Print and postage prices vary by format, volume, region and postal rate changes, so get quotes from your mail house; USPS posts current rates on usps.com.
Some teams move money toward the touch that converts best once they have a season of data, or swap the cheapest touch for a postcard. The roofing direct mail ROI calculator shows how response, close rate and job value turn into cost per signed roof.
Crew capacity vs response
Mail that books more inspections than you can sell, or more jobs than you can install, is wasted twice: you paid for the lead and the owner waits and goes elsewhere. Work it backwards. If your crews can install, for example, 25 roofs a week from mid-April, and your sales team closes a known share of inspections, you can estimate how many inspections each week can absorb. Size each drop to that number, and split a large list into waves by ZIP code instead of mailing everything on one day.
Waves also make the season steadier. A drop every week or two, each to a different group of ZIP codes, keeps the phones busy without a spike your call center cannot answer.
Tracking codes and phone numbers per drop
Give every drop its own tracking phone number or short code, and log the drop date, the ZIP codes, and the piece count. When a homeowner calls, the number tells you which touch and which wave brought them. Without this, every spring result is one blended number, and next year’s budget is a guess.
Fall as the second season
Fall is the natural second window: owners who delayed in spring want it done before winter, and crews often have open weeks after the summer peak. Plan it the same way, backwards from the last install weeks before cold weather. Refresh the list first so homes re-roofed over the summer come out, remove spring customers and open leads, and run a shorter sequence. For selling in a market without storms, see how to sell a roof without a storm and retail reroof marketing without storms.
Where Scout Data fits
Scout Data delivers lists of homes by roof age and roof condition, with homes already re-roofed taken out, owner-occupied, with the owner on title and the mailing address.
We send the list to your mail house on the schedule you set, so the spring drops and the fall drops each go out on a fresh list. See the retail reroof page or the old roofs dataset.
Frequently asked questions
When should a roofer start planning spring direct mail?
Count back from the week your crews can start installing. In a cold market where installs start in April, that means pulling the list in January, finishing creative and print in February, and dropping the first touch in late February or March.
How long does USPS Marketing Mail take to deliver?
Marketing Mail is slower and less predictable than First-Class Mail. Delivery windows vary by distance, entry point and volume, so plan a cushion of a week or more and check the current service standards on usps.com before you set drop dates.
Is fall a good second season for roofing mail?
Yes, in most markets. Owners who put off a roof in spring often want it done before winter, and crews usually have open weeks after the summer rush. A smaller fall sequence to the same filtered list, with spring responders removed, fits well.